Commercial Projects

Main Entrance.jpg

Key Aspects

Yakama Power 
Yakama Power New Office Building 

RJS was the Prime Contractor on this Design-Build 7,500sf, wood frame Office Facility. This administration building included offices, kitchen, breakroom, fitness center, showers, conference area, and a customer lobby with ballistic glass drive through window & office space.

Outside.png

Passages Family Support

Passages Peer Respite Center 

RJS Construction Inc was the Prime Contractor for the 4200 sq ft nonprofit temporary housing facility built for the clients of Passages Family Support, a behavioral health service provider of Washington State. This building blended the amenities of a commercial business and a residential home for the clients and staff.

Key Aspects 

2017_08_25 Catholic Charities New Early

Key Aspects

Catholic Charities
New Early Learning Center

RJS was the Prime Contractor on this Design-Build 16,750sf, wood frame, slab on grade building for Catholic Family Child Services. State-of-the-art facility included offices, classrooms, medical exam, library, and playground. 

"If I were to find a word to describe why I chose RJS, I would say that the word would be consistency."

-John Young, President and CEO, Catholic Charities, USA

Key Aspects


Nez Perce Tribe
Clearwater River Resort

RJS teamed with Swinerton Builders for the $14M Expansion and Renovation of Clearwater River Resort for the Nez Perce Tribe. Included the addition of a 500,000 gallon water tank to provide additional storage and fire suppression support for the hotel, casino and RV Park & Campsites. 

Clearwater.jpg
Legends.jpg

Key Aspects

​11,175 Square foot childcare center. New construction single story, slab-on-grade building. The exterior of the building incorporates Native American designs and architectural features. Project also included a fenced play area, asphalt driveway, and parking spaces. 

 

Yakama Nation

Legends Casino Childcare Facility

Hogue Ranches

Office and Warehouse

"Quality workmanship, excellent subcontractors, honest communication."

Ron Harle, Manager, Hogue Ranches

Hogue Ranches Office (64).JPG
Hogue Ranches Warehouse (48).JPG

"RJS Construction has outstanding quality control.  What they build looks better and lasts longer than other contractors."

Ron Harle, Manager, Hogue Ranches

photo.JPG

A Sample of Our Projects for the Catholic Diocese of Yakima

  • Holy Spirit Kennewick Church Hall

  • St. Andrew's Rectory Ellensburg 

  • St. John's Remodel Cle Elum

  • Holy Family Baptismal Font

  • Holy Family School Kitchen

  • Parking Lot Improvements

  • St. Paul Cathedral School Maintenance

  • St. Juan Diego Parish Roof Replacement

  • Carroll Children's Center

  • New Diocesan Offices and TI

  • St. Vincent De Paul TI

  • Sacred Heart Catholic Church

Key Aspects

Red Lion Hotel Renovations 

Seattle, Bellevue, Richland, Pasco, Kennewick, Yakima and Coeur d'Alene

RJS design assisted and completed the renovations for the lobby of the Red Lion.

The Kennewick project was the first to be performed and the client was so pleased with the work done that the other projects were soon negotiated.  Red Lion Hotels Corporation has been a repeat client for over 20 projects since first contracting with RJS in 2007.

Red Lion Bellevue.jpg
Apple Valley Eye Exterior.JPG

Apple Valley Eye Clinic

Key Aspects

An eye clinic measuring 3,700 SF, including 6 patient rooms, 2 pre-test rooms, 2 offices, meeting room, reception, waiting area, and a product showroom. Prior to construction of this facility RJS demolished the existing structure to make room for the new clinic.

Key Aspects

Zirkle Fruit

Shipping Center and Cold Storage

This project for Zirkle Fruit consisted of a refrigerated staging area for the shipping/receiving of apples. This building was constructed of sandwich panel concrete tilt-up exterior walls, a steel joist & deck roof system, and an office area that utilized steel studs with a composite concrete floor deck.

ZirkleShipWarehouse1.jpg

Diocese of Spokane
Mary Queen of Heaven Church 

Key Aspects

Removed and reinstalled stained glass windows for historic restoration. Replaced non-painted broken, cracked or missing pieces and removed loose paint on the outer surface of the millwork. Repaired cracking and damaged plaster as well as molding and fresco touch up. 